Overview

OPG is refurbishing the four Pickering B units to extend the station roughly 30 years past their original retirement date. It is the largest capital project in Canada by stated value, and the single biggest factor in whether Ontario keeps its nuclear baseload through the 2030s.

Owner
Ontario Power Generation
Province
Ontario
Location
Pickering, ON
Category
Nuclear
Phase
Construction
Estimated cost
$26.8 billion
Expected completion
2035

Cost figure covers four units, as stated Jan 15, 2026.

Latest update

Ranked the largest active capital project in Canada.

ReNew Canada's 2026 Top100 placed Pickering B first at $26.8 billion, with nuclear taking four of the top six spots.

Jan 15, 2026

Project timeline

  1. Jan 15, 2026

    Ranked the largest active capital project in Canada.

    ReNew Canada's 2026 Top100 placed Pickering B first at $26.8 billion, with nuclear taking four of the top six spots.

    Source ↗

Recent news

Sources

Also reported as: Pickering Generating Station Refurbishment · Pickering Nuclear Refurbishment · Pickering B Units 5-8

Tracked since Sep 21, 2026

Looking for something else? Browse every tracked project.